Stick Farm

Project Start Date: April 2006
Project End Date: December 2012

Stick Farm Area consists of seven 19 privately owned farms. The primary objective of the project was to provide a safe and reliable source of potable water to the rural community of Stick Farm.

The project resulted in the implementation of the following infrastructure:

  • Supply and installation of mechanical and electrical equipment at Stick Farm Pumpstation
  • Construction of 500 m³ Stick Farm reservoir and Stick Farm Pumpstation
  • Construction of 50mm-110mm diameter x 9,5 km long hdpe/uPVC gravity/rising bulk/reticulation pipelines in stick farm

The infrastructure was commissioned in 2010.

Beneficiaries: The estimated present day population of the Stick Farm Area is 3 200 people. The project population for a design horizon of 20 years is 5 300 people assuming 2,5% growth per annum.

PROJECT OVERVIEW

LOCATION:

Ugu District Municipality Port Shepstone KwaZulu Natal RSA

CLIENT:

Ugu District Municipality

VALUE:

R3.8 million / US$ 0.48 million

SERVICES:

  • Planning & Preliminary Design
  • Cost Estimating
  • Contract Administration
  • Commissioning/handover
  • Engineering Design
  • Procurement
  • Construction Monitoring

ELEMENTS:

  • 500m3 rc reservoir
  • Pumpstation
  • Pumping main
  • 9.5km reticulations