Ndaya Water Supply

Project Start Date: June 2008
Project End Date: December 2014

ZIYANDA Consulting cc was appointed to provide consulting services for the entire bulk water supply and reticulation infrastructure for a rural community in KwaZulu Natal. ZIYANDA Consulting’s brief included the following:

  • Assessments of existing bulk and reticulation infrastructure (condition and capacity) delivering up to 4Ml/day
  • Design and implementation of bulk and reticulation infrastructure to provide full water supply coverage.

The project resulted in the implementation of the following infrastructure:

  • 18km of pumping main of diameter 150mm,
  • 2 No. Pumpstations delivering approximately 60l/second of water,
  • Over 40km of reticulation pipelines
  • 5Ml storage reservoirs
  • Ancillary works

Project Phase (about 70%) have been completed successfully and commissioned. The remainder are under phased implementation.

PROJECT OVERVIEW

LOCATION:

Mzinyathi District Municipality Msinga KwaZulu Natal RSA

CLIENT:

Mzinyathi District Municipality

VALUE:

R10 million / US$ 1.2 million

SERVICES:

  • Planning & Preliminary Design
  • Engineering Design
  • Cost Estimating
  • Procurement
  • Contract Administration
  • Construction Monitoring
  • Commissioning/handover

ELEMENTS:

  • Feasbility
  • Business Plan and Construction Management for pumping mains, pumpstations, reservoirs and reticulation