Kokstad Waste Water Treatment Works Upgrade

Project Start Date: October 2010
Project End Date: October 2011

This project involved the Supply and Installation of Mechanical and Electrical and Equipment for Kokstad Wastewater Treatment Works Extension (upgrade by a rating of 3.5Ml/day) and the following work was done:

  • the design, supply, installation, testing and commissioning of mechanical mixers to be installed in the anaerobic and anoxic zones of the bioreactor,
  • The design, supply, installation, testing and commissioning of five surface aerators comprising aerators, gearboxes and motors (4No. x 55kW; 1No. x 10kW) for the aeration of mixed liquor in the aerobic zones.
  • The supply, installation, testing and commissioning of equipment for two 21.5 metre diameter secondary clarifiers complete with rotating bridge and scraper; inlet pipe, stilling chamber, electric power cabling and controls,
  • The supply, installation, testing, and commissioning of:two return activated sludge submersible pumpsets,
  • The supply, installation, testing, and commissioning of:two, 3-speed mixed liquor recycle (A recycle) pumps,
  • Supply and installation of electrical equipment,
  • Supply and installation of screens, overflow weirs, etc and other associated ancillaries
  • Refurbishment of equipment on the existing waste water treatment stream of the works.

PROJECT OVERVIEW

LOCATION:

Sisonke District Municipality Kokstad RSA

CLIENT:

Sisonke District Municipality

VALUE:

R1 million / US$ 0.13 million

SERVICES:

  • Planning & Preliminary Design
  • Cost Estimating
  • Contract Administration
  • Engineering Design
  • Procurement
  • Construction Monitoring

ELEMENTS:

  • Waste Water treatment plant: Mechanical and electrical Equipment Upgrade