Gamalakhe Water Supply Scheme

The proposed Gamalakhe Water Supply Project: Security of Supply aims to provide safe and reliable source of potable water to Gamalakhe Township and the surrounding rural settlement, within District Municipality:

  • Construction of 600mm dia x 3.0km steel pipeline from Shelly Beach off-take to Uvongo off-take
  • Construction of 450mm dia x 6.0km steel pipeline from Uvongo off-take to Gamalakhe.
  • Construction of 4.5Ml reservoir in Gamalakhe.
  • Construction of 0.5Ml reservoir and a pump-station building at the Ugu Sports Complex
  • Mechanical and Electrical Equipment

 

Beneficiaries: The population that benefited is 42 368

PROJECT OVERVIEW

LOCATION:

Ugu District Municipality RSA

CLIENT:

Ugu District Municipality

VALUE:

R89 million

SERVICES:

  • Planning & Preliminary Design
  • Engineering Design
  • Cost Estimating
  • Procurement
  • Contract Administration
  • Construction Monitoring
  • Commissioning/handover

ELEMENTS:

  • 10km x 600mm diameter steel pipeline