







Project Start Date: February 2008
ZIYANDA Consulting cc successfully completed and commissioned the Gamalakhe Water Scheme – Security of Supply project implemented on behalf of Ugu District Municipality in February 2008 to guarantee the secure supply of portable water to Gamalakhe Township and surrounding areas. ZIYANDA had been appointed by Ugu District Municipality to provide the following services.
The Gamalakhe Water Supply Scheme – Security of Supply project was implemented through four (4) contracts as follows:
| Contract | Description |
| UGU-07-1197-2012 | Construction of 600mm Diameter x 3.0km Steel Pipeline from Shelly Beach Off-take to Uvongo Off-take |
| UGU-07-1258-2012 | Supply and installation of 2 x Pumps (180l/s and 197m Head) at the Gamalakhe Pumpstation |
| UGU-07-1259-2012 | Construction of 500m³ Reservoir and Gamalakhe Pumpstation Building at Ugu Sports Complex |
| UGU-07-1260-2012 | Construction of 450mm Diameter x 6.5km Steel Pipeline from Ugu Sports Complex to Gamalakhe Reservoir |
Beneficiaries: Approximately 42,368 people had benefited directly on completion of the project.
Ugu District Municipality RSA
Ugu District Municipality
R76 904 558.23 incl. VAT.
+27 (0) 33 346 0673
ziyanda@ziyandaconsulting.co.za
35 Ridge Road, Scottsville
ZIYANDA Consulting is a firm of dedicated consulting engineers offering people centred solutions in civil, structural, and electro-mechanical engineering, as well as project and contract management
Subscribe on us and receive latest projects update.
Copyright © Ziyanda Consulting 2025. All Right Reserved.