Project Start Date: June 2008
Project End Date: December 2014
ZIYANDA Consulting cc was appointed to provide consulting services for the entire bulk water supply and reticulation infrastructure for a rural community in KwaZulu Natal. ZIYANDA Consulting’s brief included the following:
- Assessments of existing bulk and reticulation infrastructure (condition and capacity) delivering up to 4Ml/day
- Design and implementation of bulk and reticulation infrastructure to provide full water supply coverage.
The project resulted in the implementation of the following infrastructure:
- 18km of pumping main of diameter 150mm,
- 2 No. Pumpstations delivering approximately 60l/second of water,
- Over 40km of reticulation pipelines
- 5Ml storage reservoirs
- Ancillary works
Project Phase (about 70%) have been completed successfully and commissioned. The remainder are under phased implementation.
PROJECT OVERVIEW
Mzinyathi District Municipality
Msinga
KwaZulu Natal
RSA
Mzinyathi District Municipality
R10 million / US$ 1.2 million
- Planning & Preliminary Design
- Engineering Design
- Cost Estimating
- Procurement
- Contract Administration
- Construction Monitoring
- Commissioning/handover
- Feasbility
- Business Plan and Construction Management for pumping mains, pumpstations, reservoirs and reticulation