Project Start Date: October 2010
Project End Date: October 2011
This project involved the Supply and Installation of Mechanical and Electrical and Equipment for Kokstad Wastewater Treatment Works Extension (upgrade by a rating of 3.5Ml/day) and the following work was done:
- the design, supply, installation, testing and commissioning of mechanical mixers to be installed in the anaerobic and anoxic zones of the bioreactor,
- The design, supply, installation, testing and commissioning of five surface aerators comprising aerators, gearboxes and motors (4No. x 55kW; 1No. x 10kW) for the aeration of mixed liquor in the aerobic zones.
- The supply, installation, testing and commissioning of equipment for two 21.5 metre diameter secondary clarifiers complete with rotating bridge and scraper; inlet pipe, stilling chamber, electric power cabling and controls,
- The supply, installation, testing, and commissioning of:two return activated sludge submersible pumpsets,
- The supply, installation, testing, and commissioning of:two, 3-speed mixed liquor recycle (A recycle) pumps,
- Supply and installation of electrical equipment,
- Supply and installation of screens, overflow weirs, etc and other associated ancillaries
- Refurbishment of equipment on the existing waste water treatment stream of the works.
PROJECT OVERVIEW
Sisonke District Municipality
Kokstad
RSA
Sisonke District Municipality
R1 million / US$ 0.13 million
- Planning & Preliminary Design
- Cost Estimating
- Contract Administration
- Engineering Design
- Procurement
- Construction Monitoring
- Waste Water treatment plant: Mechanical and electrical Equipment Upgrade