Project Start Date: May 2010
Project End Date: February 2013
The project resulted in the implementation of the following infrastructure:
- Construction of 0.25ML Cedars Reservoir and Pumpstation Building
- Supply and Installation of Mechanical and Electrical Equipment for lower KwaCele and Cedars pump stations
- Construction of 200mm diameter x 7.7km long steel pipeline from Lower KwaCele Reservoir to Cedars Reservoir
- Construction of 200mm diameter x 6.5km long steel pipeline from Cedars Reservoir to Dududu Reservoir
PROJECT OVERVIEW
Ugu District Municipality
RSA
Ugu District Municipality
R2.8 million / US$ 0.28 million
- Services:
- Planning & Preliminary Design
- Cost Estimating
- Contract Administration
- Engineering Design
- Procurement
- Construction Monitoring
- 250m3 rc reservoir
- Pumpstation
- 14.2km reticulations