Water infrastructure projects recently awarded
The following projects, managed by ZIYANDA Consulting, have been awarded recently:
Client | Contract No. | Description | Award Value | Successful Contractor |
Ugu District Municipality | UGU-07-1194-2012 | Construction of 160-63mm Diameter x 8,0km Long UPVC reticulation pipelines in Stick Farm | R2.3M | Sizabonke Civils cc t/a Pilcon Projects |
Ugu District Municipality | UGU-07-1197-2012 | Construction of 600 mm Diameter x 3.0km steel pipeline from Shelly Beach Off –Take to Uvongo Off Take | R22M | TBA |
Ugu District Municipality | UGU-07-1207-2013 | Construction of 100-300mm Diameter x 7.4 km long steel UPVC pipelines & Associated Pipe Bridge at stream crossings | R13.9M | LNY Construction & Civils |
Ugu District Municipality | UGU-07-1034-2013 | Construction of 110mm Diameter x 5 km Long UPVC reticulation pipelines in Harding. | R5.6M | LNY Construction & Civils |